A bathroom involves six or more trades working in a tiny space, and the order they work in matters more than almost anything else. Get the sequence right and the job flows. Get it wrong — the classic being tiling before waterproofing has cured — and you’ve built a failure into the walls. Here’s the correct order, and why each step depends on the last.
Think of a bathroom renovation as a relay. Each trade hands off to the next, and if one runs out of turn, the whole result suffers. This is exactly why having a single team coordinate the sequence beats managing a loose collection of subbies yourself.
1. Demolition and strip-out
Everything comes out first — fixtures, tiles, old membrane and usually the wall sheeting — back to the framing and floor. Only with the room stripped can the trades that follow see what they’re working with and do their part properly.
2. Carpentry and structural repairs
With the room open, any damaged framing, subfloor or blocking is repaired first. This is also when timber noggins are added to support wall-hung vanities, grab rails or heavy fixtures later. Fixing structure now, while everything is exposed, is far cheaper than discovering a problem after tiling.
3. Plumbing rough-in
The licensed plumber runs new water supply and drainage inside the walls and floor to suit the new layout, before anything is closed up. If you’re moving the shower, toilet or vanity, this is where that happens. Rough-in has to be right first time — it’s about to be sealed inside the wall.
4. Electrical rough-in
The licensed electrician runs cabling for lighting, the exhaust fan, power points, heated towel rails and any underfloor heating. Electrical work in a bathroom is safety-critical and zoned by proximity to water, so it must be done by a licensed electrician to the wiring rules.
The one sequence rule that matters most: waterproofing goes on after rough-in and sheeting, and tiling goes on after the membrane has cured. Reverse either of these and you’ve built a leak into the room. It’s the number-one shortcut behind expensive failures — more in why waterproofing fails.
5. Wall sheeting and preparation
Water-resistant sheeting goes up, the floor is prepared, and everything is made ready for waterproofing. Getting a flat, sound substrate here is what lets the membrane and tiles perform.
6. Waterproofing
The membrane is applied to floors and walls by an appropriately licensed trade, to the Australian Standard, and then left to cure. This is the pivot point of the whole job. Nothing should happen on top of it until it’s ready.
7. Screeding and tiling
The floor is screeded to create correct falls to the drain, then tiling begins. Good tiling is patient work — setting-out, falls and grout lines all done with care.
8. Fit-off (plumbing and electrical)
Both licensed trades return to install and connect fixtures: tapware, toilet, vanity, shower fittings, lights, fan and power points. This “second fix” only happens once tiling is done.
9. Cabinetry, glass and painting
Vanities and shaving cabinets are fitted, the shower screen and mirrors installed, and the ceiling and any painted surfaces finished. Ceilings in particular deserve attention in wet areas, where moisture and heat put paint and plaster to the test over time.
10. Silicone, clean and handover
Flexible silicone seals the movement joints, the room is cleaned, and you’re walked through everything with your certificates handed over.
Read that list again and one thing stands out: almost every stage depends on the one before it being finished properly. Skip ahead, and the problem is usually sealed inside the wall where it’s expensive to reach. That’s the whole argument for respecting the sequence, and for having someone whose job it is to protect it.
When one team owns this sequence, the waterproofer isn’t waiting on the plumber and nobody tiles over uncured membrane. That coordination is the quiet reason a job runs on time and lasts. See how we manage it on our bathroom renovations Mornington page, we work throughout Mount Martha and beyond, and you can get in touch for a quote.
Frequently asked questions
What is the correct order of trades in a bathroom renovation?
The sequence runs demolition, carpentry and structural repairs, plumbing rough-in, electrical rough-in, wall sheeting, waterproofing and curing, screeding and tiling, plumbing and electrical fit-off, cabinetry, glass and painting, then silicone sealing and handover. Each stage depends on the one before it being done correctly.
Why does waterproofing come before tiling?
The membrane is the barrier that keeps water out of the framing and subfloor, so it must be applied and cured before any tiles go on. Tiling over uncured or missing waterproofing is the single most common shortcut behind leaks and expensive failures later.
Why does the order of trades matter so much?
A bathroom is a small space with six or more trades, and each hands off to the next. If a trade works out of sequence, the result suffers and failures can be sealed inside the walls. A single team coordinating the sequence prevents these costly errors.
Should one company manage all the trades?
Having one accountable team coordinate every trade means the sequence is controlled, nobody tiles over uncured membrane, and responsibility is clear if anything needs attention. It also keeps the job moving rather than stalling while trades wait on each other.